Changes made to construction phasing in Hot Springs

HOT SPRINGS, S.D. — Construction phasing in Hot Springs has been changed with the reconstruction of the segment of U.S. Highway 385 from Detroit Street to Baltimore Avenue being halted until Spring 2023.

Additionally, work on the segment of Highway 385 from University Avenue to Baltimore Avenue will begin in mid-September and continue through December.

Weather permitting through the fall and winter months, water and sewer installation will begin in October on North River Street near the Jennings Avenue intersection and move north.

Business access will remain open at all times through the work zone, and the speed limit will be reduced down to 25 mph. Motorists are asked to be aware of suddenly slowing and merging traffic, changing work zone locations, reduced speeds through the work zone, and construction workers and equipment adjacent to the driving lanes.